RIGGING PLANFOR LIFTING STEAM DRUM 72 TO AT BOILER BY WINCH
1. GENERAL
2.PURPOSE
3. GENERAL NOTE
3.1. Inspection
3.2. Safety
- A safety officer presents all times Safety Briefing.
- Job Safety Analysis (JSA) must be carried out for all crane lifts and all other tasks that have potential risk to personnel of equipment.
- Install scaffolding where necessary to install bolt in each beam and member connection.
- Pre lift study before any lifting activity.
- Lift briefing and Safety briefing before any lift; assign responsibility to all personnel involved. (Signalman, Rigger to crane driver, etc.)
- Ensure all equipment required for installation is on hand and in position before lift i.e. Chain blocks, Lever blocks, Podgy, Drifts, Hammer, and Spanners. Etc.
- Tag lines must be used to control lift.
- Ground conditions must be ready before activities.
- Set up safety rope around lifting area of Steam Drum area and put notice board entered “KEEP OFF EXCEPT PERSONNEL AND CONCERNED”.
- Lifting equipment should be in certification and tagged.
- Crane and other machinery shall be inspected and certified.
3.3. Lifting
3.4. Assembly and erection
4. RESPONSIBILITY
4.1. Chief Construction
4.2. Field Engineer
4.3. Field Superintendent and Supervisor
4.4. Quality Control Engineer
4.5. Supporter Activities
5. BASIC REQUIREMENT
5.1. Schedule and Planning
Master schedule is usually provided by Main Contractor. The detailed schedule is prepared by Contractor according to his planning which is based on Main Contractor’s master schedule. The milestone and the critical path can be identified which require proper planning. The sequence of erection activities and the resources required is included in the planning.
5.2. Erection Drawing and Erection Manual
Erection drawing and manual usually provided by Vendor. The Field Engineer and Superintendent shall check all drawings intended for Steam Drum Erection. All the information required is completed and all drawings shall be of latest revision.
5.3. Packing List
Packing List shall be provided by Vendor. This included all the listing of materials, equipment and parts that are supplied.
The Packing List should indicate the quantity of the material and equipment supplied and its specification as described in the erection drawing. This will also indicate the size and the total weight of the component and the method of storage. Also the packing number and material coding is very essential.
5.4. Storage Area and Warehouse
Upon a thorough check on the drawing and the packing list, the quantity of materials and equipment is already known, including the method of storing, the size of the storage area and the warehouse can be identifying.
5.5. Resources
Identification of resources is integral part of planning and scheduling is the most essential part of the basic requirement in undertaking Structure Boiler in particular and in all jobs in general. Resources means, the materials, Labour and equipment needed to perform Structure Boiler Project.
6. PREPARATION WORK
6.1. Checking of Steam Drum Erection Drawings
This has to be done by the Chief Construction, Field Engineer, Superintendent and Supervisor to determine the correct resources needed to perform the job.
6.2. Checking of Client Supplied Material and Equipment
Checking and inspection of the materials and equipment including the spare parts is to be done by the material control. He will make sure that all materials, equipment and spare parts received from Main Contractor, conform to the quantity and the specifications started in the packing list or shipping.
6.3. Checking of Erection Materials, Equipment, Tools and Machinery
In the early stage of planning, these resources had been already identified. The schedule of mobilization as on planed schedule made by the Chief Construction and Engineer.
6.4. Checking of Labour
Labour requirement for every stage of erection job is prepared by the Chief Engineer and his erection team, which is in accordance to their planning.
7. ORGANIZATION CHART
8. STEAM DRUM ERECTION SEQUENCE
8.1. Remarks:
8.2. Preparation Works:
9. LIFTING PROCEDURE OF 72 TON BOILER DRUM
- Drum shall be delivered with center offset towards grid K1.
- Restrain the end of drum at grid K1 with chain blocks to prevent drum from hitting the column at grid K1 during its initial lift off.
- Lift the drum by approximately 100 mm and hold it for 15 minutes while all direct load bearing temporary and permanent girders and beams, winch system are checked for any undue deflections or connections (steel/hose) non conformities.
- Once the system has been cleared for safe lifting, the wood/steel/concrete blocks that are supporting the drum at ground floor are removed.
- Lift Winch 1 and Winch 2 by slowly.
- At this position, the drum shall clear the steel on both sides. A continuous monitoring on the condition of the lifting system shall be done. The watchmen shall continuous follow the drum while on its way up to check for any obstruction along the way of the drum. If there is any obstruction the watchmen will inform the lifting controller to hold the lifting until the obstruction is cleared, then resume lifting.
- Lift both ends together until the highest end is clear - above the Elev. 46500 mm.
- Lift the drum until U-Bolt connection can be made.
- After U-Bolt installation is complete, transfer the load from the lifting cables to the bolts.
- The lifting device shall be dismantled together with the temporary support to clear the way for erection work to progress.
10. LIFTING TOOLS
- Electric Winch capacities 10 ton : 2 unit.
- Tackle Block capacities 50 ton : 4 unit
- Rolling Block capacities 15 ton : 6 unit
- Rolling Block capacities 5 ton : 1 unit
- Shackle Omega capacities 50 ton : 2 unit
- Chain Block capacities 10 ton : 2 unit
- Temporary Hanger capacities 50 ton : 2 unit
- Sling 22mm 500 meter : 2 unit
- Wire Clip 7/8 inch : 6 pcs
11. RIGGING ANALYSIS
11.1. Winch
11.2. Load Distribution
Figure 1- Load of Steam Drum 72 ton
- Accessories 8 ton
- Total Load 80 ton
Load Distribution Every Point:
11.3. Anchorage Points
- Lead Line Load = ( Load)/(Parts of Line at Load)
- Lead Line Load = ( 40 ton)/(6 line)=6,667 ton ~ 7 ton
- Load on structure = Load + Lead Line Load
- Load on structure = 40 ton + 7 ton = 47 ton
11.4. Safety Factor of Sling
12. LIFTING ARRANGEMENT
13. WINCH ARRANGEMENT
14. U BOLT HANGER INSTALLING
Steam Drum at elevation +47750 mm.
Adjust top of U bolt elevation by chain block.
0 Comments:
Post a Comment